What her planned timeline is for the delivery of new free schools approved in principle, including the (a) key stages from approval to opening, (b) typical duration of each stage and (c) factors impacting deliv
New free school projects that are centrally delivered by the department typically progress through six key stages: pre‑feasibility (including finding a suitable site), feasibility, procurement, design and planning, construction and handover, and post‑comp...