The Westminster lensArchive · Written questions · 134 tabled · 121 answered

Written questions by George.

Every parliamentary written question tabled by Andrew George this session, with the full answer and department. Back to the MP page.

Department:All (134)Department for Environment, Food and Rural Affairs (27)Department of Health and Social Care (22)Department for Science, Innovation and Technology (17)Cabinet Office (14)Treasury (14)Department for Energy Security and Net Zero (10)Department for Work and Pensions (10)Department for Business and Trade (6)Ministry of Defence (4)Ministry of Housing, Communities and Local Government (3)Department for Education (2)Scotland Office (1)

Showing 110 of 10 · Department for Energy Security and Net Zero

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

What steps his Department is taking to ensure that reforms to planning permission are matched by improvements to the processes for acquiring land and rights over land, so that grid connection projects are not delayed by unresolved land rights issues.

Reply

DESNZ has worked closely with stakeholders to understand the extent to which current land access, rights and consents processes delay and add costs to rollout of electricity network infrastructure required for delivering clean power by 2030 and accelerating the UK’s transition to Net zero. This has included looking at where there might be opportunities to learn from approaches to other utilities. Government’s assessment was set out in a consultation in Summer 2025 on proposed reforms to these processes. We expect to publish the response in the coming quarter.

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

What steps are in place to allow land rights negotiations and Section 37 applications to proceed in parallel.

Reply

Consent is required under section 37 of the Electricity Act 1989 to install or keep installed certain overhead electric lines. Land rights negotiations and section 37 applications can proceed in parallel. The Secretary of State would normally expect land rights to be in place before granting a section 37 consent, although as set out in the Guidance, in some circumstances he may consent ahead of this on condition that the work must not proceed until the relevant agreements with landowners and/or occupiers are in place.

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

If his Department will engage with industry and landowner representatives to develop innovative, respectful statutory land access powers to support the delivery of Clean Power 2030.

Reply

The government regularly engages with industry and landowner representatives to explore opportunities for streamlining the land access, rights and consents processes. This work recently culminated in the publication of a consultation in summer 2025, which provided a formal opportunity for stakeholders to respond to a set of proposed reforms to these processes. Prior to the consultation, the government established a Working Group to generate and appraise ideas to improve land access, rights and consenting processes, many of which were included in the consultation. The Working Group met six times between April 2024 and May 2025.

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

If his Department will commit to developing new statutory mechanisms which provide electricity network operators with outcome-certain, timely, and cost-effective land access, while maintaining strong relationships with landowners.

Reply

DESNZ has worked closely with stakeholders to understand the extent to which current land access, rights and consents processes delay and add costs to rollout of electricity network infrastructure required for delivering clean power by 2030 and accelerating the UK’s transition to Net zero. This has included looking at where there might be opportunities to learn from approaches to other utilities. Government’s assessment was set out in a consultation in Summer 2025 on proposed reforms to these processes. We expect to publish the response in the coming quarter.

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

What consideration has been given to aligning the statutory powers available to electricity network operators for land access with those available to water and telecoms utilities, to ensure timely and cost-effective delivery of network upgrades.

Reply

DESNZ has worked closely with stakeholders to understand the extent to which current land access, rights and consents processes delay and add costs to rollout of electricity network infrastructure required for delivering clean power by 2030 and accelerating the UK’s transition to Net zero. This has included looking at where there might be opportunities to learn from approaches to other utilities. Government’s assessment was set out in a consultation in Summer 2025 on proposed reforms to these processes. We expect to publish the response in the coming quarter.

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

What assessment has been made of the potential impact of current land rights processes on the UK's ability to meet its Clean power 2030 targets.

Reply

DESNZ has worked closely with stakeholders to understand the extent to which current land access, rights and consents processes delay and add costs to rollout of electricity network infrastructure required for delivering clean power by 2030 and accelerating the UK’s transition to Net zero. This has included looking at where there might be opportunities to learn from approaches to other utilities. Government’s assessment was set out in a consultation in Summer 2025 on proposed reforms to these processes. We expect to publish the response in the coming quarter.

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

What estimate he has made of the additional costs and delays to customers resulting from the current statutory processes for acquiring land and rights for electricity network upgrades.

Reply

DESNZ has worked closely with stakeholders to understand the extent to which current land access, rights and consents processes delay and add costs to rollout of electricity network infrastructure required for delivering clean power by 2030 and accelerating the UK’s transition to Net zero. This has included looking at where there might be opportunities to learn from approaches to other utilities. Government’s assessment was set out in a consultation in Summer 2025 on proposed reforms to these processes. We expect to publish the response in the coming quarter.

27 Feb 2026·Department for Energy Security and Net Zero·Answered
Asked

What steps his Department is taking to introduce statutory turnaround times for consents teams handling compulsory purchase and necessary wayleave applications, to reduce end-to-end project timelines.

Reply

The government is assessing how it can streamline land access, rights and consent processes to speed up electricity network deployment and published a consultation which ran from 8 July to 2 September 2025. The consultation proposed a raft of changes to these processes. We expect to publish our response in the coming quarter, setting out the direction of travel in this area.

30 May 2025·Department for Energy Security and Net Zero·Answered
Asked

What funding his Department (a) has provided and (b) intends to provide, including through energy company obligations, to help reduce domestic energy bills between the 2020-21 and 2030-31 financial years, broken down by (i) cash handouts, (ii) installation of (A) new gas boilers, (B) heat pumps, (C) other heating systems, (D) solar panels, (E) domestic and heat batteries (including heat batteries), (iii) replacement (1) windows, (2) doors and (3) insulation and (iv) other support.

Reply

As the first step towards the Warm Homes Plan, the Government has committed an initial £3.4 billion over the next 3 years towards heat decarbonisation and household energy efficiency, with £1 billion of this allocated to 2025/2026. The current iteration of the scheme, ECO4, runs from 2022 - 2026 with an increased value of £4 billion to accelerate our efforts to improve homes to meet fuel poverty targets. Government does not specify which types of measures should be installed in any particular property, only that the installations should be carried out by TrustMark registered installers in accordance with the relevant standards and consumer protection requirements. Deployment of measures under Government schemes are published monthly on Gov.uk: www.gov.uk/government/collections/green-home-grant-statistics, www.gov.uk/government/collections/household-energy-efficiency-national-statistics.

20 May 2025·Department for Energy Security and Net Zero·Answered
Asked

What proportion of funding to tackle fuel poverty has been allocated to home insulation.

Reply

Fuel poverty policy is devolved with the Department for Energy Security and Net Zero having responsibility for England. The Government has kickstarted delivery of the Warm Homes Plan, including an initial £1.8 billion to support fuel poverty schemes over the next 3 years. There are multiple targeted schemes in place to deliver energy efficiency measures, low carbon heating and insulation measures to low income and fuel poor households in England. Schemes include the Energy Company Obligation (ECO), the Great British Insulation Scheme, the Warm Homes: Social Housing Fund (formerly the Social Housing Decarbonisation Fund), and the new Warm Homes: Local Grant. The Government's review of the 2021 fuel poverty strategy confirms that a new plan is needed to accelerate progress to alleviate fuel poverty. We have therefore consulted on a revised fuel poverty strategy focusing on improving the energy performance of homes, supporting low-income households with energy affordability and protecting them from high prices. The consultation closed on 4 April and we are considering the responses received.

Sources
SourceUK Parliament Members API
MethodQuestion and answer text as published. Question preamble (“To ask the…”) trimmed for readability; answers shown in full.