Committee publication · Correspondence · 18 December 2025

Note to Chair of Finance Committee - Elizabeth Tower Project, December 2025

From: Finance Committee (Commons)

Summary

A note to the Finance Committee Chair detailing the Elizabeth Tower refurbishment project outcome. The £85.5m project (approved budget £89m) completed in October 2023 after significant cost growth from initial estimates. Key drivers of increases: underestimated remedial works, site discoveries, clock mechanics outsourcing, and scaffolding complexity. Audits found no material errors in final accounts.

Key findings

  • Project cost grew from £29.2m (OBC Feb 2016) to £85.5m outturn, with major increases in main works (£4.8m to £32.8m), scaffolding (£3.3m to £7.3m), and fees (£2.9m to £11.3m).
  • Site discoveries (defective structure, lead paint, asbestos) and re-measurable works underestimation (stonework required four times original allowance) were principal cost drivers; inadequate intrusive surveys identified as root cause.
  • Clock mechanics outsourcing (~£2.0m additional cost) required because Parliament's in-house specialist team lacked capacity for conservation work.
  • Scaffolding costs grew £5m from OBC owing to unique requirements (largest free-standing scaffold in Europe) only apparent after detailed design.
  • Covid costs added £7.8m to outturn. BDO audit concluded no material exceptions in final account; Broom Report identified poor contract structure (mixed pricing options, insufficient team training) but lessons now embedded in Parliamentary policy.

Tone

Factual

Topics

capital-projectsheritage-conservationprocurementproject-management

Key actors

Finance Committee, Sir Robert McAlpine, Purcell Architecture, Curry and Brown, BDO, JCBA, Broom Report

Notable line

… the fieldwork and further analysis conducted by the audit team did not identify any clear, obvious or material exceptions/errors which would necessitate withholding or delaying final account sign-off.

Key Quotes

… the fieldwork and further analysis conducted by the audit team did not identify any clear, obvious or material exceptions/errors which would necessitate withholding or delaying final account sign-off.
BDO Audit · Conclusion on Main Works Final Account including Covid Costs
Mixing of Pricing options (A&B) and bespoke amendments were ill-advised, (2) Lack of training of project team on 'new' form of contract.
Note author · Broom Report findings on contract structure
On stonework, over four times as much work as originally allowed for was needed: inadequate surveys and benchmarking could have avoided over optimism.
Note author · Key change event: re-measurable works underestimation
View original document →

Source · parliament.uk record ↗

Note to Chair of Finance Committee - Elizabeth Tower Project, December 2025 | Beyond The Vote | Beyond The Vote